Plan Your Parts and Inspections Before Plant Shutdowns | Aerodyne
Now that it’s spring, it’s time to start thinking about summer shut down! If you are planning on doing maintenance on your dust collection system now is the time to order your parts. ![]()
If you are changing bags, also look into doing the following:
- Pull your airlock off and perform any needed maintenance on it (replace bearings, change out rotors or plate, replace Vacu-Valve sleeves, etc.)
- Have someone check your exhaust fan a few weeks before shutdown so that if the fan needs rebalancing or bearings replaced, you can schedule it during the shutdown.
- Inspection of your baghouse a few months before shutdown so any damage in the housing, bad air valves, tube sheet, etc. can be replaced during the process.
- Inspect the ductwork and look for holes and dust buildup. Make sure dampers are working.
- Look into installing a cyclone pre-filter to
- Increase filter life
- Decrease compressed air usage
- Collect dust before contamination in the filters
- Inspect explosion protection equipment and have any chemical isolators/suppression equipment maintained. Be sure to have the clearance of the rotary valve measured to be sure it is still in compliance with NFPA requirements.
- Schedule an engineer led system evaluation to evaluate the system performance so any modifications can be installed during plant shutdown.
Doing the above will help you revitalize your dust collection system and make sure you get the best possible performance out of it.
For more dust collection and material handling literature, visit our website at www.dustcollectorhq.com. Case studies, testing information, and our monthly blog are all available.
To improve efficiency and safety, there is no substitute for an on-site inspection by an experienced expert. Click here to connect with our engineering team and discuss your application.